CABLE CORPORATION OF INDIA, Ltd.

FACTORY BUILDING MALEGAON, MIDC SINNAR

CLIENTS
Cable Corporation of India, Ltd., MIDC, Malegoan, Sinnar, Nashik.
Consultant
Shri. Pradeep Deshmukh, Mumbai.
PROJECT COST
Phase I - 10 Crore.
Phase II - 9.85 Crore.
Total Area
Phase I - 1 Lac Sq. Ft.
Phase II - 7.00 Acre Campus
Duration
Phase I - April 2008 - June 2009
Phase I - Dec 2010 - Nov 2011
Features
    Phase I -
  • R.C.C. structure, structural steel work, Color Coated Galvalime roofing for cladding.
  • Machine Foundations / U.G. water tank of capacity 4.0 lacs.
  • Asphalts Roads, Storm water drain for site development.
  • Building Constrcution main factory building - 1,07,600 sq.ft.
  • Dispatch & Partial dispatch - 15,000 sq.ft.
  • Impulse building -8200 sq.ft.
  • Maintenance Substation, cooling toner, Generator room, Meter Room, etc. - 12,000 sq.ft.
    Phase II -
  • 7.00 Acre Campus
  • R.C.C. Foundation in 7 Mtr Hard Rock
  • R.C.C. Structures Structural Steel Work
  • Structural frame & roof colour coated galvalume Roofing at 18 Mtr Height
  • Trimix RCC flooring
  • Slab at 9 Mtr & 6 Mtr Level
  • Building Constructed
  • Shed (102x38) – 41705 Sqft
  • Shed (24x24) – 6200 Sqft
  • Shed (54x24) – 13950 Sqft
  • Shed (78x12) – 10072 Sqft
  • Shed (36x12) – 4650 Sqft